Public Security Directorate Chalets
A turnkey project for the design, construction and installation of a Sewage Treatment Plant, activated sludge process based on the Sequencing Batch Reactor Technology (SBR) having the capacity of 60 m3/day.
The scope included:
-
Construction works which included inlet structure, process tanks, , treated water storage tank, electromechanical rooms and the connection to the sewer network.All Tanks are closed reinforced concrete tanks.
-
Mechanical works which included: Aerators, mixers, pumps, screening, hypochlorite disinfection system and Filters.
-
Electrical, Instrumentation & SCADA for local and remote monitoring and controlling. Works included MCC Motor Control Center with PLC for a fully automatic un-manned operation. Instrumentation including ultrasonic transmitters.