General Rehabilitation and upgrade of (1800 m3/day) WWTP

The scope included:

  • Manufacturing & replacement of a the scraper & the scum outlet.

  • Foam fighting pump & sprinklers,

  • Construction of rooms and walkways.

  • Repair, sand blasting, epoxy treatment and sealing of the steel process tanks.

  • Installing sand filters and disinfection system. 

  • Construction and Installation of grit removal System.

  • Upgrade of biological process and mixing system.

  • Upgrade of aeration system and installation of automatic turbo air blowers.