Balqaa’ Rehabilitation Center

Turnkey Project of a 2 streams Wastewater Treatment Plant (300 m3/day).

​

The scope included: 

Design & construction of the Inlet Structure, with flow measurement.

Balancing Tank, Aeration tanks (2), Sedimentation Tanks (2), Sludge Tank, Chlorine Contact Tank, Effluent Storage / Irrigation Tank, Service Building, Mechanical Rooms, Fences & Gates, Pipe Laying & Cable Laying. Equipment included Bar Screens, Air Blowers, course bubble diffusers mixing system, fine bubble diffusers Aeration System, Sand Filters & Pumps, Irrigation Pumps, Disinfection System (Hypochlorite), MCC + PLC + GSM Modem.