UNICEF WWT at 3 Schools in Rehab - Mafraq

Design and installation of a 2 Sewage Treatment Plants, activated sludge process based on the Fixed Bed Reactor Technology. As well as a greywater treatment plant and rain water harvesting systems at 3 schools in Rehab - Al Mafraq

Scope includes design, supply, install, testing, commissioning and training including all civil works.

The works included :

Construction works which included process tanks, , treated water storage tank, electromechanical rooms and the connection to the sewer network. All Tanks are closed reinforced concrete tanks.

Mechanical works which included: Blowers, pumps, hypochlorite disinfection system.

Electrical, Instrumentation & SCADA for local and remote monitoring and controlling. Works included MCC Motor Control Center with PLC for remote monitoring.

Scope also included rehabilitation of WASH units in 3 schools. 
 